Encore Boston Harbor – Battery Energy Storage System

Location:
1 Broadway Everett, MA
General Contractor:
Suffolk Construction
Owner:
Wynn Resorts
Size:
4MW

Project

This project consisted of the installation of two 15KV Feeders, two 15KV disconnect switches, two 15KV/480V Dry – Type Transformers, two 480V Switchgear, (16) Battery & Inverter Skids to complete a fully functional peak shaving battery energy storage system. It also entailed the installation and testing of 1,100 Lithium-Ion Batteries. We utilized our in-house CAD department and self-performed Trimble survey systems. We were able to complete the coordination, layout, and installation of the underground raceway system for the customer.