Raytheon, 15kV Feeder Replacement

Project Scope: MEC Power Group replaced two (2) 13.8 kV feeders, which required the installation of new 15kV metering equipment within a new cabinet, and approximately 300 linear feet of 4x5” PVC concrete-encased duct bank.  MEC also provided re-energization and testing of equipment.
Field Crew: 6 IBEW Local 103 electricians
Special Challenges: Work was required to be performed during off-hours with the use of generators to provide temporary power.  The project was completed and the facility re-energized and tested within a 12-hour period.

 